How to compare GPU cloud quotes on the same basis

The price per GPU-hour is where a quote starts, not what it costs. Before you compare two offers, bring them to the same basis: same scope, every fee included, the hours you are actually billed, and the cost of any cash you pay upfront.

1. Check the quotes cover the same thing

Line the offers up against your brief: GPU model and variant (SXM or PCIe), number of nodes, interconnect, storage, location, start date and term. An offer that differs on any of these is not cheaper or dearer, it is a different product. Ask the operator to requote on your brief before you compare prices.

2. Put every fee into one price

Storage, data egress, support, set-up and onboarding fees can be included in one offer and billed apart in another. Add every recurring fee over the term and every one-off fee, and divide by the GPU-hours you receive. That gives one all-in price per GPU-hour per offer.

3. Count the hours you are billed

Contracts bill a month in different ways: 730 hours (the yearly average), 720 hours (30 days), or the actual hours of each calendar month. Over a given period, the calendar has a fixed number of hours, so the convention changes what you pay per hour you can actually use.

Six months from 1 Feb 2027Hours billed per GPUVersus the calendar
Calendar hours4,344Same
730-hour months4,38036 hours more (+0.8%)
720-hour months4,32024 hours less (−0.6%)

The effect is small per hour but applies to every GPU for the whole term. The point is not which convention is right, but that both offers are compared on the same one.

4. Price the cash you pay upfront

A prepayment or a deposit is cash you hand over before you use the GPUs. It has a cost: the interest you would have earned on it. We value it at the risk-free rate of the contract currency (SOFR for dollars, €STR for euros), without any assumption about your own cost of capital.

Upfront cash also exposes you to the operator's credit: if it fails, a prepayment may not come back. That risk is real but specific to each operator, so we show it apart rather than inside the price.

5. Compare the written terms

Two offers at the same real price can still differ on what you can rely on. Check each one for a validity date, a fixed or indexed price, the uptime commitment and the credit if it is missed, the delivery date, and the options to extend or end early. An uptime commitment is a credit you can claim, not a forecast: we do not deduct assumed downtime from the price.

Worked example

32 H100 GPUs for six months from 1 February 2027. Two illustrative offers, not market quotes:

Offer AOffer B
Quoted price per GPU-hour$2.40$2.45
Month convention730 hoursCalendar hours
Storage$2,000 a month extraIncluded
Prepayment25%None
Contract value$348,384$340,570
Cost of upfront cash (SOFR 3.92%)$854$0
Real price per GPU-hour$2.51$2.45

Offer A is cheaper on the headline price and more expensive in reality: about $8,700 more over the term. Its lower rate saves about $4,200, even after the extra hours billed under the 730-hour convention; storage billed apart costs $12,000, and the prepayment adds $854.

Run your own quotes through the free GPU cost calculator: it applies this method in your browser, and nothing you type is stored.

Next steps

Check a quote with the GPU cost calculator, or submit a requirement and we ask operators for firm offers, shown side by side. Free for buyers.